Re: working backwards

The place where forum members can discuss anything related to project management.

Re: working backwards

Postby lucian » Tue Aug 07, 2012 9:46 am

Normally to create a backward scheduling you create an "end project marker" (basically a milestone) and move it to the date you want the project to end then, from this marker simply link tasks by "Start to Finish" dependencies instead of default "Finish to Start" , please see picture attached:
Attachments
BackwardSchedule.png
BackwardSchedule.png (89.63 KiB) Viewed 8295 times
lucian
 
Posts: 243
Joined: Fri Mar 26, 2010 3:09 pm

Re: working backwards

Postby andrew » Tue Aug 07, 2012 10:15 pm

Thanks for this

it works just as i want!

:D

regards

andrew
andrew
 
Posts: 3
Joined: Mon Aug 08, 2011 3:30 am