Postby danhawthorne » Tue Jan 10, 2012 4:19 pm

I have a simple project created with 5 major tasks and roughly 35 subtasks. There are quite a few precedents/dependents and the project covers about 90 days but my Gantt chart does not show a critical path. Why not? Also, can I dictate what is the critical path or does the program control what comprises the critical path? Thank you.
Posts: 3
Joined: Tue Jan 10, 2012 4:05 pm

Re: Critical Path

Postby lucian » Tue Jan 10, 2012 4:51 pm

To see critical path simply go to Gantt view and click the small critical path icon on the toolbar.
If you still can not see critical path address an email to support (please attach your .xrp)
Posts: 243
Joined: Fri Mar 26, 2010 3:09 pm