Allocation of Time

Do you need help related to existing features or need a new feature? This is the place where you can tell about it.

Allocation of Time

Postby danhawthorne » Tue Jan 10, 2012 4:15 pm

Does anyone know if you can allocate the amount of each day a specific resource dedicates to a specific task? Right now, I have a resource working on 3 tasks simultaneously over the course of a 30 day period. The program shows that person as utlized 24 hours/day (3 tasks x 8 hours/day each) for the whole 30 days. What I am trying to do is have that resource dedicated 33% to each of the 3 tasks during that month so that he is utilized just 8 hours/day.
danhawthorne
 
Posts: 3
Joined: Tue Jan 10, 2012 4:05 pm

Re: Allocation of Time

Postby lucian » Tue Jan 10, 2012 4:55 pm

If you want to allocate just a fraction of resource's work on a task then in Gantt, select that task and go to resources tab at details; there you can select the assignment you want to change and type 0.33 at units instead of 1 (which is the default)
lucian
 
Posts: 243
Joined: Fri Mar 26, 2010 3:09 pm

Re: Allocation of Time

Postby danhawthorne » Tue Jan 10, 2012 8:02 pm

Thank you.
danhawthorne
 
Posts: 3
Joined: Tue Jan 10, 2012 4:05 pm