Split at task on multiple resources

Do you need help related to existing features or need a new feature? This is the place where you can tell about it.

Split at task on multiple resources

Postby Nicod44 » Thu Oct 27, 2011 11:36 am

is they're a way to have a task with 2 resources, one is working five day a week and second resource work each monday ?
Posts: 1
Joined: Thu Oct 27, 2011 10:37 am

Re: Split at task on multiple resources

Postby lucian » Thu Oct 27, 2011 5:21 pm

Sure, simply set appropriates calendars for each resource, thus each resource will work according to his calendar by default
If this is not your case (both resources have regular calendars for example) you can simply break on task in two, on the first part (of one day) have both resources, on the other (of four days) have only one resource
Posts: 243
Joined: Fri Mar 26, 2010 3:09 pm