Postby LKirkes » Thu Mar 22, 2012 2:01 pm

Is there a way to generate a Spend Plan Report so I can see Project Budgeted Cost per Day and export it to a Spreadsheet?
LKirkes
 
Posts: 4
Joined: Thu Mar 22, 2012 1:30 pm

Re: Spend Plan

Postby lucian » Thu Mar 22, 2012 4:55 pm

You can quickly go to the Task Sheet view and see there your costs per day/week/month/minute :) They are available from Project level to task level. You can print them, etc
lucian
 
Posts: 243
Joined: Fri Mar 26, 2010 3:09 pm

Re: Spend Plan

Postby LKirkes » Thu Mar 22, 2012 5:01 pm

Thanks for responding rapidly. This works very well!